Murano Residence 1 construction photos
85 photos from 9 site inspections, newest first. The percentage is how much of Murano Residence 1 was built on the day of each visit.
29 January 2019100% built
28 October 201897% built
1 July 201876% built
18 March 201865% built
26 December 201745% built
19 September 201723% built
5 June 201711% built
21 February 20173.7% built
15 November 20162.4% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.