Glamz Residence construction photos
127 photos from 13 site inspections, newest first. The percentage is how much of Glamz Residence was built on the day of each visit.
22 October 2020100% built
22 June 202097% built
24 March 202095% built
16 October 201993% built
4 July 201991% built
18 March 201985% built
23 December 201880% built
17 September 201866% built
23 May 201858% built
4 February 201843% built
27 September 201722% built
21 May 20177.4% built
29 November 20162.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.