Azizi Shaista Residence construction photos
84 photos from 9 site inspections, newest first. The percentage is how much of Azizi Shaista Residence was built on the day of each visit.
9 March 2021100% built
1 February 202199% built
13 February 202066% built
12 September 201957% built
14 July 201956% built
17 April 201956% built
22 January 201942% built
23 August 201720% built
25 April 201713% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.