Azizi Plaza Hotel Apartments construction photos

90 photos from 10 site inspections, newest first. The percentage is how much of Azizi Plaza Hotel Apartments was built on the day of each visit.

3 November 2021100% built

24 January 202195% built

19 February 202085% built

12 September 201982% built

14 July 201978% built

22 January 201973% built

1 August 201870% built

6 December 201739% built

23 August 201723% built

25 April 201714% built

Back to Azizi Plaza Hotel Apartments construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.