Avenue Residence 6 construction photos

40 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Avenue Residence 6 was built on the day of each visit.

30 April 202682% built

15 January 202661% built

13 October 202535% built

30 June 202520% built

14 October 20246.6% built

1 February 20240% built

Back to Avenue Residence 6 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.