Lilium Tower construction photos

68 photos from 8 site inspections, newest first. The percentage is how much of Lilium Tower was built on the day of each visit.

29 September 2026100% built

14 August 202698% built

27 April 202691% built

30 December 202565% built

8 July 202531% built

12 February 202514% built

8 July 20241.9% built

4 July 20230% built

Back to Lilium Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.