Fairway Villas 3 construction photos

52 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Fairway Villas 3 was built on the day of each visit.

7 July 202649% built

17 March 202638% built

25 December 202527% built

9 September 202522% built

16 May 202511% built

28 January 20252.6% built

16 September 20240.3% built

12 February 20240% built