Samana Ivy Gardens 2 construction photos

21 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Samana Ivy Gardens 2 was built on the day of each visit.

18 June 202615% built

10 February 20268.8% built

16 October 20257.0% built

2 July 20255.5% built

27 November 20241.6% built

1 March 20240% built

Back to Samana Ivy Gardens 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.