Skip to content

Address Residences Zabeel construction photos

21 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Address Residences Zabeel was built on the day of each visit.

25 June 202615% built

4 February 202610% built

6 October 20258.7% built

10 June 20254.8% built

19 February 20251.1% built

5 February 20240% built

Back to Address Residences Zabeel construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.