50 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Orla Infinity By Omniyat was built on the day of each visit.

26 August 202661% built

16 March 202640% built

24 November 202525% built

2 September 202515% built

5 May 20259.1% built

2 July 20241.3% built

1 April 20240.2% built

12 July 20230% built

Back to Orla Infinity By Omniyat construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.