Ocean House construction photos
72 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Ocean House was built on the day of each visit.
3 September 202681% built
9 June 202671% built
27 February 202666% built
4 November 202549% built
16 July 202530% built
27 March 202521% built
13 December 202412% built
10 September 20248.7% built
13 March 20246.1% built
27 November 20234.1% built
5 June 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.