Azura Residences construction photos

48 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Azura Residences was built on the day of each visit.

7 May 202669% built

4 February 202650% built

24 October 202527% built

9 June 202516% built

17 December 20245.2% built

17 May 20240% built

Back to Azura Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.