Ocean Point construction photos
25 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Ocean Point was built on the day of each visit.
21 April 202627% built
8 December 202515% built
17 July 202510% built
24 April 20256.7% built
19 February 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.