Marina Views construction photos
16 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Marina Views was built on the day of each visit.
5 May 20267.1% built
19 January 20266.3% built
30 July 20252.4% built
17 April 20250.4% built
2 July 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.