Maison Elysee Ii construction photos
35 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Maison Elysee Ii was built on the day of each visit.
4 September 202623% built
6 July 202618% built
30 March 202615% built
3 December 202511% built
30 June 20252.5% built
19 January 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.