95 photos taken by Dubai Land Department engineers at 13 site inspections, newest first. The percentage is how much of Seven City Jlt was built on the day of each visit.

14 May 202628% built

8 May 202428% built

7 November 202326% built

10 July 202321% built

1 March 202315% built

13 June 202213% built

12 October 202113% built

6 June 202111% built

19 October 20208.3% built

2 April 20208.1% built

7 November 20198.1% built

3 July 20198.0% built

19 February 20197.5% built

Back to Seven City Jlt construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.