Lumo construction progress

Lumo is 23% built at the site inspection of September 2026. Developer Wog Capital Real Estate Development. Completion registered for February 2027.

23%

Built, at the site inspection of 11 September 2026

Registered completion date
February 2027
Construction started
August 2025
First registered
October 2026
Developer
Wog Capital Real Estate Development
Units
54
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لومو
Project number
4527
Site inspections
1

Schedule

Lumo has one site inspection on record so far, which is not enough to measure a pace. A pace needs two inspections at least a month apart.

Site inspections

Context

Own a unit in Lumo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lumo be completed?
The registered completion date is February 2027. Developers can apply to extend the date, so check the register before relying on it.
How much of Lumo is built?
23%, measured at the site inspection on 11 September 2026.
Who is building Lumo?
The registered developer is Wog Capital Real Estate Development.
Which bank holds the escrow account for Lumo?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.