Greenspoint construction photos

30 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Greenspoint was built on the day of each visit.

21 July 202643% built

21 April 202626% built

25 November 20258.0% built

30 July 20251.4% built

22 January 20250% built

Back to Greenspoint construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.