Enqlave By Aqasa construction photos

40 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Enqlave By Aqasa was built on the day of each visit.

22 September 202670% built

11 June 202658% built

22 January 202640% built

13 October 202525% built

8 July 202516% built

29 March 20240% built

Back to Enqlave By Aqasa construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.