51 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Damac Lagoons - Morocco 2 was built on the day of each visit.

17 July 202665% built

14 April 202660% built

11 November 202546% built

10 June 202536% built

27 January 202520% built

30 September 20248.8% built

20 May 20244.1% built

7 December 20230.4% built

2 June 20230% built

Back to Damac Lagoons - Morocco 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.