Skip to content

Bayz 101 By Danube construction photos

34 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Bayz 101 By Danube was built on the day of each visit.

12 August 202610% built

16 April 20269.3% built

23 December 20258.3% built

29 September 20255.5% built

3 July 20255.1% built

4 March 20253.5% built

6 December 20240.4% built

23 April 20240.2% built

19 January 20240% built

Back to Bayz 101 By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.