340 Riverside Crescent construction photos
44 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of 340 Riverside Crescent was built on the day of each visit.
18 August 202655% built
12 May 202643% built
30 January 202637% built
19 September 202531% built
9 May 202521% built
11 February 202513% built
5 November 20249.6% built
14 May 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.