Damac Lagoons - Mykonos construction photos
69 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Damac Lagoons - Mykonos was built on the day of each visit.
30 September 202681% built
9 July 202680% built
13 May 202677% built
27 November 202561% built
19 June 202553% built
20 February 202544% built
26 September 202421% built
17 April 20247.0% built
21 August 20230.6% built
4 May 20230.3% built
1 February 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)





























.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)






.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)