Damac Lagoons - Lagoon Views 5 construction photos

31 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Damac Lagoons - Lagoon Views 5 was built on the day of each visit.

17 July 202642% built

1 April 202636% built

7 November 202520% built

1 July 202510% built

18 September 20240.6% built

6 February 20240% built

Back to Damac Lagoons - Lagoon Views 5 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.