Azizi Jewel construction photos
21 photos taken by Dubai Land Department engineers at 4 site inspections, newest first. The percentage is how much of Azizi Jewel was built on the day of each visit.
7 October 202643% built
13 April 202627% built
9 December 202516% built
24 April 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.